A refurbishment project plan needs to connect the intended property use with the work required for handover.
Start before inviting prices. Contractors need enough information to understand the scope, restrictions and completion requirements.
This guide covers management arrangements for landlords and investors. Technical design, surveys, consents and statutory appointments need appropriate professional input for the property and works.
1. Establish the property’s starting condition
Gather the information already available: drawings, surveys, records of services and relevant property documents. Identify information gaps that could affect the work.
A management walk-through can record visible conditions and outstanding questions. It does not replace specialist investigation or a professional survey.
Record access restrictions, occupation, storage, deliveries and working-hour constraints. Check how the work interfaces with neighbours, shared spaces or existing tenants.
Create an assumptions list. An unknown item should have an investigation action, an owner and a required date.
2. Write a scope that contractors can price
Break the works into packages or areas. Describe the required output, quantity basis, specification and any client-supplied items.
State what is excluded. Include clearance, protection, waste, making good, testing and documentation where these form part of the requirement.
For example, a kitchen package needs more detail than “replace the kitchen”. Identify the agreed design, services interfaces, appliances, finishes and acceptance checks.
Record provisional items separately. The client should understand which prices rely on assumptions or later investigation.
Use a single controlled enquiry pack so bidders receive the same information.
3. Compare contractor proposals on the same basis
Prepare a comparison schedule showing the scope, price, exclusions, assumptions and proposed duration for each quotation.
Ask questions before selection. Clarify supply responsibilities, access requirements, dependencies and the documents required at completion.
A lower headline price may exclude part of the required work. Compare the total scope you expect to receive.
Check the information needed for contractor selection and appointment with the appropriate advisers. Confirm who will manage the construction work and its interfaces.
Keep the agreed clarifications with the appointment records. Our contractor management guide covers delivery coordination after appointment.
4. Build a programme around dependencies
Sequence investigation, design information, procurement, preparation, installation, inspections and handover. Include decisions and access requirements.
Identify items with long ordering periods. A contractor’s start date may depend on materials, approved drawings or another trade finishing.
For an illustrative bathroom refurbishment, strip-out might expose conditions requiring investigation before first-fix work can proceed. Record the review point and decision route.
Ask each delivery party to confirm its inputs and expected durations. Review overlaps carefully where several trades need the same space.
A programme needs enough detail to support the next few weeks of work. Update it using current evidence.
5. Set up the budget and change process
Keep the approved budget alongside the forecast final cost. Record commitments and remaining work consistently.
Identify allowances for unresolved scope and risks. Explain the assumptions behind them and who can authorise their use.
Agree how contractors will submit proposed changes. The record should explain the work, reason, cost basis and time effect.
Client approval needs to follow the contract’s authority and notice provisions. Record decisions promptly and update the cost forecast.
For the calculation structure, read how to track a project budget and forecast.
6. Agree site reviews and progress evidence
An investor managing remotely needs a defined reporting arrangement. Agree visit frequency, photographs, programme updates and escalation routes.
Photographs should identify the location, date and work shown. Pair them with records of completed activities and outstanding constraints.
A progress review should address what changed since the last review and what needs action next. Record responsibilities and required dates.
Decide who checks technical work and what inspections are required. Project management attendance does not replace specialist inspection or statutory approval.
Where a critical activity is approaching, confirm readiness before the planned start.
7. Plan handover before the final week
List completion requirements at the planning stage. These may include specified tests, certificates, instructions, keys, warranties and outstanding-work records.
Assign responsibility for collecting each item. Check that contractor scopes include the required documents.
Agree how defects or incomplete items will be recorded and reviewed. Separate a physical inspection from contractual acceptance and any required certification.
Confirm who can accept work on the client’s behalf. Follow the agreed contract process when recording completion.
The handover tracker should show the owner, status and evidence for each required item.
Use a proportionate management pack
For a straightforward refurbishment, a compact pack can contain the scope, quotation comparison, programme and cost tracker.
Add the contract records, change register, action list and handover tracker. Keep current versions available to the relevant people.
Construction work carried out for a business can involve commercial client duties under CDM 2015. Check the HSE guidance and arrange appropriate appointments.
SCOPE provides property refurbishment project management for landlords, investors and developers. Include the property location, planned works and current stage when sending an enquiry.